Home / Energy / Tedzani IV ahead of schedule despite Covid-19 woes
Energy

Tedzani IV ahead of schedule despite Covid-19 woes

May 29, 2020 / Tawonga Nyirenda Mayuni
...

The Electricity Generation Company (EGENCO) says construction of Tedzani IV Hydropower plant is ahead of schedule despite coronavirus disease (COVID-19) woes.

EGENCO says in a statement posted on its Facebook page that boarder restrictions imposed by a number of countries as a containment measure against the pandemic is making it difficult for the company to import equipment for the project.

However, EGENCO states that if the situation improves and equipment starts flowing into the country smoothly, the project will be completed way ahead of time.

“Currently, 84% of the works at the Tedzani hydropower plant have been finished, and the contractor is engaged in final power house civil works, continuing spiral case and turbine installations,” reads the statement from the power utility.

The project is scheduled to be commissioned in September 2021 but EGENCO says with the outstanding progress being made, the 18MW plant may be commissioned in February 2021, all things being equal.

The project is being financed using proceeds of a Japanese grant of US$52-million while EGENCO is contributing US$4.8-million.

Japanese contractor Mitsubishi Corporation is executing the civil works for the power plant in a joint venture arrangement with Calik Enerji of Turkey.

Share this:

Leave a Comment


Comments

The establishment of a stable and self-sustaining ecosystem, but not necessarily the one that existed before mining began. In many cases, complete restoration may be impossible, but successful remediation, reclamation, and rehabilitation can result in the timely establishment of a functional ecosystem.



The cleanup of the contaminated area to safe levels by removing or isolating contaminants. At mine sites, remediation often consists of isolating contaminated material in pre-existing tailings storage facilities, capping tailings and waste rock stockpiles with clean topsoil, and collecting and treating any contaminated mine water if necessary.